DTRS ROLLOUT 70 locations

Duration: 30 Months

Overview: Transport for NSW has begun installing a Digital Train Radio System throughout the 1455 Kilometre electrified rail network, bounded by Kiama, Macarthur, Lithgow, Bondi Junction & Newcastle. This project will see the installation of masts and other communication equipment at approx. 250 locations within the rail corridor and more than 60 sites in tunnels.

Contract Value: $6 Million